For the normal sleepwear route using standard fabric qualities, sample preparation takes 7–10 working days and bulk production takes 25–30 working days. Each period starts from the readiness conditions agreed for that stage, including the required information, materials, approvals and relevant payment arrangements.
Your complete launch plan also needs time for customer review, revisions, additional development, testing and transport. Tell us the date you need goods at your destination and what that date represents: a warehouse booking, photography session, wholesale delivery or retail launch.
| Stage | What needs to be ready | What the planned date should mean |
|---|---|---|
| Sample start | Defined sample task, relevant artwork and specifications, available materials and agreed fee arrangements | The start of that sample round |
| Sample completion | Making and sample checks completed | The sample is ready for the agreed handoff; international receipt is a separate event. |
| Customer review | Sample and supporting records received by the decision-maker | Consolidated feedback or approval is due. |
| Production start | Applicable approvals, specification, material and order readiness, with relevant payment conditions met | The agreed bulk stage begins. |
| Factory release | Product, inspection, packing, documents and commercial release conditions complete | Goods can be handed over on the agreed delivery basis. |
| Destination receipt | Transport, clearance and receiving arrangements completed | Goods reach the specified destination or booked warehouse slot. |
Working days and calendar days are different. The project calendar should identify factory working days, holidays, buyer review time and service-provider availability instead of adding headline ranges as if every day were interchangeable.
For a two-piece knit set with an established fabric quality, available artwork and a defined base size, a sample round can cover specification review, pattern preparation, material and component checks, cutting, sewing, measurement and preparation of the sample record.
At the end of the round, the handoff can include the sample version, photographs, measurements and any material differences. The 7–10 working-day range concerns that defined task. A new print approval, custom component, extra size set or further revision receives an appropriate place in the plan.
Some tasks do not depend on the same decision. Grading can be reviewed after the fit direction is accepted while a color is still under review. Approved packaging can be prepared while other permitted work continues.
Material purchases, custom printing or other commitments require the relevant authorization. Agree the scope, cost and change consequences before advancing them. A proposed parallel schedule should show exactly which decision releases each task.

A new fabric quality, late print file, revised size specification, unapproved label, changed destination or additional testing can affect different parts of the schedule. We review the affected work, explain the dependency and update the next decision and delivery expectation.
Consolidated feedback helps avoid conflicting revision rounds. One person can collect comments from design, merchandising and quality, then send a versioned decision. The record should state which details remain approved so they are not reopened accidentally.
A multi-stage engineering project may use an 18-week planning example with material comparisons, several sample stages, wash observations, a selected pilot and bulk work. That is a project-specific development plan, not the standard lead time for every sleepwear order.
Likewise, a 200-unit pilot selected for a larger complex order does not become a minimum before a 30-unit order. Scope and validation needs determine the development plan. Plan a seasonal launch.
No. We agree the start of the relevant task after its required inputs and conditions are ready. An initial conversation can begin much earlier.
No. Completion, dispatch and receipt are separate milestones. Identify the person and address receiving the sample to reduce avoidable handoffs.
It can reuse valid approvals where specifications remain unchanged. Materials, colors, documents and available production scheduling still need review; a revised fit or material can reopen development work.
Yes. Send the required date, current readiness and acceptable options. We can assess the scope and available route before confirming a project-specific plan.